Activists Taking NRC to Court Over Seabrook Station

Several groups have filed paperwork to challenge Seabrook Station's 20-year license renewal.

Submitted by Doug Bogen

Seacoast Anti-Pollution League

 

Find out what's happening in Hampton-North Hamptonwith free, real-time updates from Patch.

Three environmental groups (Beyond Nuclear, Seacoast Anti-Pollution League and the New Hampshire Chapter of the Sierra Club) have taken the U.S. Nuclear Regulatory Commission (NRC) before the U.S. Court of Appeals for the First Circuit (Boston, MA) in a legal challenge to NextEra Corporation’s application to of New Hampshire’s Seabrook nuclear generating station application from 2030 to 2050. 

The public’s legal suit was filed in Boston on August 16th after the NRC’s five member Commission unanimously reversed an earlier ruling of the agency’s own licensing board admitting the citizen groups into the re-licensing hearing on the future of offshore deepwater wind in the Gulf of Maine as an energy alternative to a 20-year license extension of the nuclear power station. The groups claim that the Commission’s decision to overrule the licensing board decision has caused “procedural injury” and violates the Atomic Energy Act (AEA) and the National Environmental Policy Act (NEPA). 

The citizen groups want the court to remedy this injury by ordering NRC to re-admit the groups back into Seabrook hearing process to review the wind energy alternative to the relicensing of the nuclear power station for 2030 to 2050. Oral arguments by the parties in the case are likely to be heard in the Boston federal court by early 2013.

 “We want full and fair disclosure on the abundance of deepwater wind energy in the Gulf of Maine and its rapid development as an electricity alternative to more dirty, dangerous and expensive nuclear power,” said Paul Gunter, a spokesperson for Takoma Park, Maryland-based Beyond Nuclear. “There is an affordable, renewable and jobs-generating energy future beyond nuclear, and the Gulf of Maine is the fertile site for the innovative development of deepwater wind generated electricity,” Gunter said.

“As more and more questions mount up regarding integrity of the plant foundations and spent fuel management, it's all the more important that we have a serious, fair and honest public discussion about the increasingly viable power alternatives before giving the go-ahead to Seabrook Station many more decades into the future," said Doug Bogen, Executive Director of Seacoast Anti-Pollution League.  "This legal appeal aims to retain that right and to hold NRC accountable for their increasingly irrational and dysfunctional decisionmaking process in light of recent events here and around the world," he concluded.

In May 2010 NextEra Seabrook made application to the NRC to extend their current 40-year operating license of the Seabrook nuclear power plant in Seabrook, NH which expires in 2030 for another 20 years through 2050.  The three environmental groups petitioned the NRC on October 20, 2010 in request of a public hearing and charged that the power company did not conduct an adequate environmental review of less harmful energy alternatives as required by the National Environmental Policy Act (NEPA). Specifically, the groups presented expert documents excluded by NextEra from its application demonstrating that offshore deepwater wind is a reasonable and less environmentally harmful energy alternative to the Seabrook license extension in 2030.  On February 15, 2011, the NRC Atomic Safety Licensing Board issued an Order granting the environmental groups a hearing as provided under NEPA to require the industry to take a “hard look” at a current plan to generate 5 Giga-watts (5000 Megawatts) of interconnected deepwater wind energy farms floating 10 to 50 miles offshore in the Gulf of Maine by 2030. On February 25, 2011, NextEra appealed the licensing board Order to the 5-member Commission. On March 8, 2012, the Commission issued an Order upholding the NextEra appeal and denying the three parties admission to a NEPA hearing.

The Petitioners’ August 16, 2012 legal brief to the U.S. Court of Appeals for the First Circuit is posted at http://www.beyondnuclear.org/storage/seabrook-renewables/seabrook-appeal/seab_lra_1stcir_brief_06162012.pdf

Find out what's happening in Hampton-North Hamptonwith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here